«Karabatan Utility Solutions» LLP

Project:Construction of industrial infrastructure of SEZ
Status:Construction stage
Product:Technical gases:
Nitrogen;
Technical air;
Instrument air;
Period of constraction: 2018-2021.

Water treatment and wastewater treatment:
Sour water;
Technical water;
Demineralized water;
Water purification;
Period of implementation: 2018-2021.

Gas Turbine Power Plant construction is in progress (Capacity - 310 MW):
Combined Cycle Power Plant will be used to generate and supply electric power and HP steam;
The planned launch date is 2020.
Description:Construction of SEZ "NIPT" infrastructure facilities
Contacts:Tel: +7 7122 556 039; Email: info@kus.com.kz